Environmental Impact Assessment (EIA)
Key Notes
Environmental Impact Assessment is a systematic process for identifying, predicting and evaluating the likely environmental impacts of a proposed project before important approval decisions are made.
Objective: Integrate environmental considerations into development planning and decision-making.
Indian legal framework: Environment (Protection) Act, 1986, and the EIA Notification, 2006, including subsequent amendments.
Regulatory authorities: The Ministry of Environment, Forest and Climate Change (MoEFCC), Expert Appraisal Committees (EACs), and State Environment Impact Assessment Authorities (SEIAAs), depending on the project.
Screening: Determines whether and how a proposal is subject to assessment under the applicable framework.
Scoping: Identifies key environmental issues and the scope of the study.
Baseline study: Documents existing environmental conditions.
Impact prediction: Estimates likely impacts on air, water, land, biodiversity and communities.
Public consultation: Provides a process for gathering concerns from affected people and other stakeholders, where required.
Appraisal: Expert examination of the proposal and assessment documents.
Environmental Management Plan (EMP): Specifies mitigation measures, monitoring arrangements and responsibilities.
Environmental clearance: Prior clearance is required for projects covered by the applicable notification, subject to its provisions and exemptions.
Key Pointers for UPSC
EIA is primarily a preventive decision-support tool, not merely a post-construction pollution audit.
The EIA Notification, 2006, replaced the earlier 1994 notification.
Category A projects are appraised at the central level; Category B projects generally fall under state-level appraisal, subject to applicable provisions.
Category B projects may be further classified as B1 or B2 according to the applicable framework.
Public consultation is not uniformly mandatory for every project; exceptions and specific procedures exist.
EIA considers both adverse impacts and possible mitigation measures.
Strategic Environmental Assessment (SEA) generally evaluates policies, plans and programmes, whereas project-level EIA assesses specific proposed projects.
MCQs
Q1. The primary purpose of Environmental Impact Assessment is to:
Assess environmental impacts before project approval decisions.
Calculate only the financial profitability of a project.
Replace all environmental legislation.
Conduct environmental monitoring only after construction.
Correct answer: 1) Assess environmental impacts before project approval decisions.
Explanation: EIA helps authorities identify potential environmental damage and evaluate mitigation measures before making relevant decisions.
Q2. The EIA Notification, 2006, was issued under which Act?
Water (Prevention and Control of Pollution) Act, 1974
Environment (Protection) Act, 1986
Air (Prevention and Control of Pollution) Act, 1981
Biological Diversity Act, 2002
Correct answer: 2) Environment (Protection) Act, 1986.
Explanation: The notification establishes the framework for prior environmental clearance of specified projects.
Q3. Which of the following statements about public consultation in EIA is correct?
It is compulsory for every project without exception.
It allows relevant public concerns to be considered where the applicable rules require it.
It occurs only after a project has been completed.
It replaces scientific environmental assessment.
Correct answer: 2) It allows relevant public concerns to be considered where the applicable rules require it.
Explanation: Public consultation is an important component of the EIA process, but the applicable framework provides exceptions and specific requirements.